2010 Mcintyre Updates
  • 1/2010: The McIntyre Square is continuing the wood framing and installation of the utilities.

  • 2/2010: The wood framing has been completed and work will commence on the exterior façade of Building A. Renovation work has commenced on Building B. Tenants; Proforma Printing, Casa Jimenez and Le Sun Tanning Salon, are open during construction.

Building A

Building B

  • 3/2010: Construction for Building A includes electrical work and framing. Building B is continuing frame work.

Building A

Building B

  • 4/2010: In Building A, the stucco is going up in preparation for the brick façade. In Building B, the framing has been completed. Preparation for stucco work to commence.

Building A

Building B

  • 5/2010: The stucco for Building A's façade has been applied and have started framing for the side façades. Building B is being prepared for the application of the stucco. Interior demolition has been completed for Building C and have started the wood framing.

Building A

Building B


Building C

Top

  • 6/2010: Building A exterior façade is nearing completion with the commencement of the exterior paint. The stucco for Building B has been applied. Building C is being prepared for stucco. Renovation of Building G has begun with the frame work.

Building A

Building B

Building C

Building G

  • 7/2010: Exterior paint has been completed for Building A. Stucco for Building B has been applied, next step is the exterior paint. Building C is being prepared for application of stucco. Frame work continues with Building G.

Building A

Building B

Building C

Building G

  • 8/2010: The exterior lighting has been installed for Building A. Exterior paint has been completed for Building B and Building C, and are ready for the installation of the exterior lighting. Façade renovations have begun on Building D and E. Wall sheathing of Building G and F has been completed and is being prepared for the application of stucco.

Building A

Building B

Building C

Building D

building f in during construction phase

Building F

  • 9/2010: Buildings A, B and C are waiting commencement of site work in order to start installation of store fronts. Wood framing continues for Building D and G. Demolition commenced of the former Del Mar Restaurant.

Building A

Building B

Building C

Building D

building f in during construction phase

Building G

Top

  • 10/2010: Stucco work for Buildings D and G commenced this month. Demolition of the former Del Mar Restaurant has been completed (which is the location for Building F).

Building D

Building F


Building G
  • 11/2010: Buildings A and B have decorative lighting installed, Building B's store fronts are being installed. Grading has begun for the parking lot.

Building A

Building B

Building D

Building G

Top

  • 12/2010: Storefronts have been completed for Buildings A, B, and C. Stucco is being applied on Building D. Building E's block walls are going up. Foundation work for Building F has commenced, with block walls to go after Building E has been completed. Building G's stucco and paint have been completed, storefronts currently being installed.

Building A

Building B

Building C

Building D

Building E

Building F


Building G