| | | | 2010 Mcintyre Updates - 1/2010: The McIntyre Square is continuing the wood framing and installation of the utilities.
 - 2/2010: The wood framing has been completed and work will commence on the exterior façade of Building A. Renovation work has commenced on Building B. Tenants; Proforma Printing, Casa Jimenez and Le Sun Tanning Salon, are open during construction.
 |  | | Building A | Building B | - 3/2010: Construction for Building A includes electrical work and framing. Building B is continuing frame work.
 |  | | Building A | Building B | - 4/2010: In Building A, the stucco is going up in preparation for the brick façade. In Building B, the framing has been completed. Preparation for stucco work to commence.
 |  | | Building A | Building B | - 5/2010: The stucco for Building A's façade has been applied and have started framing for the side façades. Building B is being prepared for the application of the stucco. Interior demolition has been completed for Building C and have started the wood framing.
 |  | | Building A | Building B |  | | Building C | Top - 6/2010: Building A exterior façade is nearing completion with the commencement of the exterior paint. The stucco for Building B has been applied. Building C is being prepared for stucco. Renovation of Building G has begun with the frame work.
 |  | | Building A | Building B |  |  | | Building C | Building G | - 7/2010: Exterior paint has been completed for Building A. Stucco for Building B has been applied, next step is the exterior paint. Building C is being prepared for application of stucco. Frame work continues with Building G.
 |  | | Building A | Building B |  |  | | Building C | Building G | - 8/2010: The exterior lighting has been installed for Building A. Exterior paint has been completed for Building B and Building C, and are ready for the installation of the exterior lighting. Façade renovations have begun on Building D and E. Wall sheathing of Building G and F has been completed and is being prepared for the application of stucco.
 |  | | Building A | Building B |  |  | | Building C | Building D |  | | Building F | - 9/2010: Buildings A, B and C are waiting commencement of site work in order to start installation of store fronts. Wood framing continues for Building D and G. Demolition commenced of the former Del Mar Restaurant.
 |  | | Building A | Building B |  |  | | Building C | Building D |  | | Building G | Top - 10/2010: Stucco work for Buildings D and G commenced this month. Demolition of the former Del Mar Restaurant has been completed (which is the location for Building F).
 |  | | Building D | Building F |  | | Building G | - 11/2010: Buildings A and B have decorative lighting installed, Building B's store fronts are being installed. Grading has begun for the parking lot.
 |  | | Building A | Building B |  |  | | Building D | Building G | Top - 12/2010: Storefronts have been completed for Buildings A, B, and C. Stucco is being applied on Building D. Building E's block walls are going up. Foundation work for Building F has commenced, with block walls to go after Building E has been completed. Building G's stucco and paint have been completed, storefronts currently being installed.
 |  | | Building A | Building B |  |  | | Building C | Building D |  |  | | Building E | Building F |  Building G | Top |
| | |
| |