| | | | Mcintyre Square - April 2011 Updates - 4/2011: Building A, B, and C are having the concrete poured for the front side walks and trees are being planted in front of Building B. Roofing is completed for Building D. Roofing and plaster are being installed onto Building E. Framework commences for Building F. Decorative lighting is completely installed on Building G. Construction has started on Buildings H & I.
 |  | | Building A | Building B |  |  | | Building C | Building D |  |  | | Building E | Building F |  Building G |  Building H & I | Top |
| | |
| |