| | | | Mcintyre Square - January 2011 Updates - 1/2011: Building A: the plumbing trench work is commencing. Building B - the shell has been completed. Building C - Decorative lighting and installation of roofing is nearing completion. Building D - continuing utility work. Building E - The footings have been poured and block wall is going up. Building F - Footings are in place and waiting for start of block wall. Building G - Roofing is completed and decorative lighting is being installed.